There is much interest generated
in the construction industry of late what with the proposed Construction
Industry Payment and Adjudication Bill 2011 (CIPA). Many professional bodies
have jumped on the bandwagon in offering courses and seminars to key
construction industry officials to try to explain the Bill of Parliament and
how the Bill when passed in Parliament will affect them. It has been hinted
that the Bill will be passed this March 2012. This would mean that companies in
the construction industry should arm itself and be ready for the new regime of statutory
adjudication. This is the era of adjudication in the construction industry.
Why CIPA? The construction
industry themselves have been pushing the government to enact this piece of
legislation since 2003 to address the cash flow problems plagued by the
industry. The primary objective of the proposed Act is to address critical cash
flow issues in the construction industry. It aims to remove the practice of
conditional payments (‘pay when paid’ and ‘pay if paid’) and reduce payment
default by establishing a cheaper, speedier system of dispute resolution in the
form of adjudication. According to the provisions of CIPA every construction contract
made in writing that relates to construction work carried out in Malaysia would
be affected by the regime of adjudication. This would essentially mean that if
you have entered into a construction contract and there is a problem with
regards to payment, an adjudication process can be commenced either by you or
against you. A construction contract can be a construction work contract and or
a construction consultancy contract.
To this extent, the parties will
be subjected to compulsory adjudication or statutory adjudication. This would
mean that both parties will be dragged into the adjudication process which is
dictated by the provisions of CIPA. The provisions of CIPA does not however
affect natural persons entering into a construction contract in respect of a
building wholly intended for his own occupation and is four storeys and below.
Be that as it may, would
adjudication stop your right to arbitration or to go to court to litigate
matters? The answer is No. The purpose of adjudication is to hurry along cash
flow and facilitate payment in the construction industry. Parties are free to
opt for arbitration or court litigation to deal with the legal matters
concerning the same. CIPA simply provides a statutory right for the parties to
demand payment for work done and to create a simple process to ensure that a
decision and payment is made. This of course is in the form of adjudication as
a process. In fact, the parties
can commence adjudication and concurrently arbitrate or litigate the matter as
well. Of course, common sense would dictate that the adjudication process will
be terminated if the dispute is decided by arbitration or the court before the
adjudication decision can be made. If however, the adjudication decision comes
first then it is a binding decision and payment must be made.
In summary, the statutory adjudication
has the following characteristics -
1. It
is a mandatory and statutory process that does not require the agreement of the
parties’ to commence the process.
2. It
offers a much faster process compared to arbitration and court litigation
because the time frame is as prescribed by the proposed CIPA itself. It is the
only form of dispute resolution that has a statutory time period in which the
dispute must be resolved in forty five (45) working days.
3. It
provides a binding decision on a payment dispute.
4. The parties can choose their own adjudicator or request for Kuala Lumpur Regional Centre of Arbitration [KLRCA] to choose an
adjudicator on their behalf.
There are many procedures to be
complied with by the parties and the time frame is dictated by the provisions
of CIPA. The entire adjudication process including the time required to decide
the case would take approximately one hundred (100) working days. So how do you go about starting the
adjudication process? The adjudication process can be summarised by the
following steps -
1. Payment Claim - The unpaid party serves
a Payment Claim on the non-paying party. The non-paying party would then serve
the Payment Response on the unpaid party in reply to the claim within 10
working days. (Either party has a right to refer the dispute to adjudication)
2. Initiation of Adjudication - The
adjudication proceeding is thereby initiated by the serving of a Notice of
Adjudication served by the claimant on the respondent.
3. Nomination of Adjudicator - An
adjudicator is thereby nominated by the agreement of both parties in the
dispute within 10 working days from the service of the notice or to request for
the adjudicator to be nominated by the Director of the KLRCA. The KLRCA has 5
working days to nominate the same.
4. Adjudication Claim - Once the
adjudicator is nominated and has accepted the terms and conditions and relevant
fees, the claimant is to serve the Adjudication Claim on the respondent within
10 working days upon receipt of the acceptance by the adjudicator whereupon the
respondent is to then serve the Adjudication Response on the claimant within 10
working days; the claimant may then serve a further Adjudication Reply within 5
working days.
5. Commencement of Adjudication - The
adjudication would then begin. KLRCA shall be informed of the commencement. The
adjudicator shall direct that reasonable proportion of the adjudicator’s fees
in equal shares be deposited in advance to the Director of KLRCA as security. Parties
can represent themselves or choose to be represented namely by a lawyer.
6. Decision - The Adjudicator has to reach
a decision not later than 45 working days from the service of the Adjudication
Response or Adjudication Reply, whichever is later. An adjudication decision
which is not made within the specified period is void. The adjudicator may also
direct full payment of the fees and expenses to be deposited with the Director
of KLRCA prior to the release of the adjudication decision to the parties. A
copy of the decision shall be provided not only to the parties but a copy must
be served on the Director of KLRCA as well.
Hence it is important to nominate
the correct adjudicator and if in doubt, reliance should be placed on the KLRCA
to appoint one on your behalf. The KLRCA has been appointed the adjudication
authority in Malaysia by virtue of Part V of CIPA, thus setting the standard
terms of appointment, fees for adjudicators and setting the competency
standards and criteria for adjudicators.
It is not
clear whether CIPA would effectively address the cash flow problems in the
construction industry but Malaysia is one of five countries who have opted to
adopt this form of legislation. The other countries are the United Kingdom,
some States and Territories in Australia, New Zealand and Singapore. We can
only wait and see.
CIPA does not affect natural persons!
ReplyDeleteConstruction Companies Australia